The New Toilet Block
Construction planning had to be precise to ensure that the most disruptive works – such as excavations, foundations and drainage – were completed before the busy tourist season began.
Challenges during construction included unexpectedly hard bedrock, discovery of uncharted electrical services not picked up by scans or surveys and freezing conditions in shaded parts of the site. These issues were addressed through felxible resource management & additional work shifts.
Key control measures included, adjusting the size and location of the compound throughout the project. Strict gated access and clear, text and pictorial signage. Public awareness training for all site operatives, focusing on assisting confused or lost visitors.
The Noisest and most disruptive works were scheduled ahead of the tourist season. Noisy activities were paused while large tour groups were boarding the steamship and deliveries were restricted to early mornings.