Project Name: Tranquil Hotel

Project Name: Tranquil Hotel

Services: Construction, Interiors & Facilities Management

Completed: 2025

This project required the complete recommissioning, repair & partial refit of a 168 bedroom hotel. The hotel had lain closed down, dormant and in disrepair for 3 years, but had also suffered from many years of neglect causing complete failure of much of the M&E plant. A large section of the hotel had also been destroyed by water ingress due to burst pipework and a lack of heating & any proper decommissioning procedures.

Scope of Works

 

  • Planning
  • Structural Repairs
  • Ventilation – AHU and air con maintenance & replacements
  • Plumbing & Heating
  • Joinery
  • Power & Lighting
  • Bedroom & En-Suite Renovations
  • Interior design 
  • Decorations 
  • Plastering
  • Flooring
  • Grounds Maintenance
  • External Facade maintenance
  • Replacement of BMS main control panels
  • Upgrading & replacing emergency lighting systems
  • Fire Stopping works
  • Fire Door replacements
  • Replacement of full fire alarm systems to L1
  • Replacement electric radiators
  • Bird and pest control implementation

What we did

 The hotel was populated to 26% total capacity within the first 6 months of the project, which brought with it mutiple challenges as major construction works were still in operation to replace roof mounted air handling plant, installation of replacement fan coil units to every inner ring bedroom on the 1st floor, strip out, refurbishment & recommissioning of water damaged rooms on the 2nd floor and replacement of the BMS main control panels together with multiple work packages for the upgrading and replacement of the emergency lighting systems, fire door replacements, fire stopping to improve fire barriers as per the fire risk assessment, replacement of the full fire alarm system to L1 & latterly the replacement of the full heating system.

Project Management

 

This required careful segregation of live work areas, highly visible barriers and warning notices in 10 languages, together with constant planning and project breifings with site contractor staff and hotel management, to clearly communicate live work areas and no-go zones. These measures only intensified & became more important as the hotel then filled to 100% occupancy within one year and then advanced to 200% by the close of the contract.

The Challenges

Key challenges were:

  1. Keeping service users informed of the changing pattern of workflow: requiring careful planning of how access and egress, as well as emergency access would operate as the live working zone progressively shifted around the hotel.
  2. Maintaining minimum notice periods: whenever access was required into a service users room, the crown office dictate that the user must be given a minimum notice period of 1 week – this required careful programming and notification to ensure that works could proceed without interruption.
  3. Movement of large plant & machinery: this included large cranes, MEWPS, Roll on roll off skip lorries and delivery trucks onto site. This required clear signage, protective barriers and a banksman (sometimes two) to ensure nobody tried to cut across a planned traffic route.