The hotel was populated to 26% total capacity within the first 6 months of the project, which brought with it mutiple challenges as major construction works were still in operation to replace roof mounted air handling plant, installation of replacement fan coil units to every inner ring bedroom on the 1st floor, strip out, refurbishment & recommissioning of water damaged rooms on the 2nd floor and replacement of the BMS main control panels together with multiple work packages for the upgrading and replacement of the emergency lighting systems, fire door replacements, fire stopping to improve fire barriers as per the fire risk assessment, replacement of the full fire alarm system to L1 & latterly the replacement of the full heating system.